Overall progress28%
Key Facts
- Contractor
- Bechtel KSA
- Budget
- SAR 1.9B
- Start
- 2024-05-20
- End
- 2028-02-28
- Health
- 81%
- Open issues
- 22
- Delay
- 0 days
Tasks
- Substation 02 cable pullingIn Progress
- Asphalt overlay – km 14 to 18Pending
Issues
- Subcontractor manpower shortage – Zone 4Medium
Site Reports
SR-2212 — 2026-05-21
Trench works km 12–14 complete.