NEOM Site Infrastructure Package

NEOM, Tabuk Region · Infrastructure · Client: NEOM Company

On Track
Site

Roads, utilities and substations for NEOM phase one infrastructure.

Overall progress28%

Key Facts

Contractor
Bechtel KSA
Budget
SAR 1.9B
Start
2024-05-20
End
2028-02-28
Health
81%
Open issues
22
Delay
0 days

Tasks

  • Substation 02 cable pullingIn Progress
  • Asphalt overlay – km 14 to 18Pending

Issues

  • Subcontractor manpower shortage – Zone 4Medium

Site Reports

  • SR-22122026-05-21

    Trench works km 12–14 complete.

Documents

  • Method Statement – Earthworks.pdf8.7 MB
  • Shop Drawings – Substation 02.pdf18.4 MB