IDIssueProjectSeverityStatusRaised
I-301Concrete cube strength below spec – Pour 42Riyadh Residential TowerHighOpen2026-05-18
I-302MEP valves not delivered to siteJeddah Commercial ComplexCriticalOpen2026-05-19
I-303Marble shipment held at customsDiriyah Hospitality Fit-OutCriticalInvestigating2026-05-20
I-304Subcontractor manpower shortage – Zone 4NEOM Site Infrastructure PackageMediumOpen2026-05-15
I-305Safety violation – PPE non-complianceDammam Warehouse DevelopmentMediumResolved2026-05-10
I-306Façade panel dimensional mismatch – L12Riyadh Residential TowerHighInvestigating2026-05-16
I-307Water seepage in basement – B2Jeddah Commercial ComplexHighOpen2026-05-14
I-308Backup generator failed test runDammam Warehouse DevelopmentMediumInvestigating2026-05-13
I-309Drawing revision conflict – Lobby ceilingDiriyah Hospitality Fit-OutLowResolved2026-05-09