← Back to projectsDelayed
Diriyah Hospitality Fit-Out
Diriyah, KSA · Hospitality Fit-Out · Client: Diriyah Gate Development Authority

Luxury hospitality interior fit-out for the Diriyah heritage district.
Overall progress54%
Key Facts
- Contractor
- El Seif Engineering
- Budget
- SAR 310M
- Start
- 2024-02-10
- End
- 2026-04-30
- Health
- 48%
- Open issues
- 19
- Delay
- 27 days
Tasks
- Marble cladding QC walkthroughAt Risk
- Ceiling lighting fit-out – LobbyPending
Issues
- Marble shipment held at customsCritical
- Drawing revision conflict – Lobby ceilingLow
Site Reports
SR-2213 — 2026-05-21
Marble shipment delayed at customs.
Documents
- Material Submittal – Marble.pdf5.4 MB